-
Baloch Incorporate, Pakistan
Grab the Packages
Pricing
- Excavation and earthwork
- Anti-termite soil treatment
- On-site representation
- Quality control inspections
- Schedule claim preparation/defense
- Project phasing development
- Retaining Wall
- foundation, columns, beams & slabs
- Staircase and Mumty structure
- Parapet walls as per approved drawings
- Internal and external plaster
- Floor PCC and porch PCC with proper compaction
- Steel door frames (16-Guage)
- Underground Water Tank & Septic tank
- Excavation and earthwork
- Anti-termite soil treatment
- On-site representation
- Quality control inspections
- Schedule claim preparation/defense
- Project phasing development
- Retaining Wall
- foundation, columns, beams & slabs
- Staircase and Mumty structure
- Parapet walls as per approved drawings
- Internal and external plaster
- Floor PCC and porch PCC with proper compaction
- Steel door frames (16-Guage)
- Underground Water Tank & Septic tank
- Project Management for Owners
- Pre-construction feasibility
- On-site representation
- Quality control inspections
- Schedule claim preparation/defense
- Project phasing development
Payment Schedule
Payment Schedule (Tentative – 6 Months Duration)
Payments shall be made according to the following construction milestones:
| Stage No |
Description |
% |
Amount (PKR) |
| 1 |
Mobilization |
15% |
0 |
| 2 |
Completion of Foundation |
20% |
0 |
| 3 |
Completion of Ground Floor |
20% |
0 |
| 4 |
Completion of First Floor Slab |
15% |
0 |
| 5 |
Completion of Brickwork & Plaster |
10% |
0 |
| 6 |
Completion of Floor PCC & Porch PCC |
10% |
0 |
| 7 |
After Completion of Grey Structure |
10% |
0 |
Clarifications & General Conditions
- The covered area mentioned is purely estimated and provided for indicative purposes only. The final covered area shall be measured on site, shade-to-shade, for final approval and clearance.
- Any work outside the defined covered area shall be treated as extra work and will be charged separately as per mutually agreed rates.
- The Contractor shall provide all necessary skilled and unskilled labour required for completion of the grey structure works.
- All construction materials including cement, steel, sand, crush, bricks, etc. shall be provided by the Client.
- The Contractor shall ensure that all work is carried out as per approved drawings, instructions, and standard construction practices.
- In case stone, rock, or any hard strata is encountered during excavation, additional excavation costs (including machinery, labour, and disposal) shall be borne by the client/owner and will be charged separately as per actuals or mutually agreed rates.
- The Contractor shall be responsible for proper execution and workmanship. Any defective work shall be rectified without additional labour cost.
- Payments shall be made according to the agreed stage-wise payment schedule.
- The Client shall ensure timely provision of materials and site access. Any delay in material supply may affect the project timeline.
- The Contractor shall maintain discipline and safety of labour at the site.
- Any additional work not included in the agreed scope shall be executed only after mutual agreement on labour rates.
- Water and electricity required for construction activities shall be provided by the Client at site, free of cost.